Court clarifies notice required to create a binding building scheme

In Randell v Uhl [2019] VSC 668, Derham AsJ has clarified the notice required before the Court will find a party to be bound by the terms of a building scheme.

Where a building scheme is established, all purchasers and their assigns are bound by, and entitled to the benefit of a restrictive covenant.

Previously, it was not entirely clear how far a purchaser would need to search the Register of Titles to be on notice as to the existence of a building scheme.

In Randell, his Honour found a building scheme had been established, but found the plaintiff not bound by its terms because the existence of a scheme was not evident on the face of the title, or any documents referred to therein:

82      … If it were sufficient notice that the Head Title in this case bears the notification of a building scheme, it would require a person interested in purchasing the Land to search the Register further than the title search indicated and to go back to the Head Title and the original, or first edition, of the Subdivision. That would render conveyancing a hazardous and cumbersome operation beyond what is reasonable to expect.

83      In summary, I am satisfied that a building scheme was established but the notification of it was not sufficient to give notice of it to the plaintiffs because a search of the title of the Land by the plaintiffs did not, and would not, reveal the existence of the scheme either directly, or indirectly by reference to any instrument referred to in the search of the title.

References to purported Building Schemes commonly appear on title documents in Victoria, but under close judicial scrutiny they are rarely proven. A question now exists whether Randell has made this process of atrophication effectively complete.

Regularising a longstanding breach of a covenant

There is a little known provision in the Planning and Environment Act 1987 (Act) that has been interpreted to allow the modification of a covenant without notice if the covenant has been breached for a period of two years or more. Section 47(2) of the Act provides:

(2)          Sections 52 and 55 do not apply to an application for a permit to remove a restriction (within the meaning of the Subdivision Act 1988) over land if the land has been used or developed for more than 2 years before the date of the application in a manner which would have been lawful under this Act but for the existence of the restriction.

Section 52 of the Act deals with advertising of applications for permits to potentially affected third parties and section 55 deals with referral to bodies such as DELWP, Telstra, VicRoads and so on.

In Hill v Campaspe SC [2004] VCAT 1399, the Tribunal explained:

26           My conclusion is that if part of a covenant is breached, and the breach continues for 2 years without any action on the part of those having the  benefit of the covenant, it is reasonable that no notice should be given of  an application to vary by removal part of the covenant of which there is a breach.  But this exemption from notice pursuant to section 47(2) of the Act should not extend to the removal of any aspect of a covenant of which there is no breach.

Although the proper interpretation of this provision is not free from doubt, this decision suggests that if a use or development has been in breach of a covenant for more than two years, a permit can be granted to remove or modify the covenant to regularise the use or development. If you rely on this provision, the relevant responsible authority under the Act should issue the permit to remove or amend the covenant without notifying other beneficiaries. However, as DP Gibson cautions, the power is limited, so any application should be judiciously drafted.